Level 4 slab poured, block shortage and crane wind stoppage
1. Summary
Level 4 column reinforcement, grids C to F, was completed and approved by the consultant for casting, and the Level 4 slab was poured between grids A to F with 42 m3 of C35 on 2026-11-04. The concrete pump broke down for 40 minutes during the pour due to a hydraulic hose failure and was repaired by the supplier mechanic. Block delivery remained short at 2000 of 5000, and masons were moved to site cleaning on 2026-11-04. HSE reported missing edge protection on Level 3 at grid 4, which was installed by 2026-11-04, and two workers on Level 2 scaffolding without safety harnesses. On 2026-11-05 the tower crane was stopped from 9am to 12 noon due to high wind, with about 3 hours lost for steel fixers and carpenters.
2. Site diary
| Date | Report | Manpower | Weather | Issues and delays |
|---|---|---|---|---|
| 02 Nov 2026 | GW-0044 Level 4 columns and slab formwork, Level 2 blockwork | 48 | Hot and clear, about 37 degrees, light wind in the morning | 1 |
| 02 Nov 2026 | GW-0045 Level 4 slab formwork, column and stair rebar, Level 2 blockwork | 46 | Partly cloudy, high 35°C, low 25°C, wind up to 9 km/h, no rain (Open-Meteo) | 1 |
| 03 Nov 2026 | GW-0046 ملاحظات السلامة: نقص حماية الحواف في الدور الثالث والعمل دون حزام أمان في الدور الثاني | حار جداً، درجة الحرارة 38 درجة | 4 | |
| 04 Nov 2026 | GW-0047 Level 4 slab pour, grids A to F | 52 | Hot, 36 degrees | 4 |
| 05 Nov 2026 | GW-0052 Tower crane stoppage due to high wind | 32 | Wind speed over 45 km/h from 9am to 12 noon | 1 |
3. Work carried out
| No. | Activity | Area / location | Status | Quantity | Remarks |
|---|---|---|---|---|---|
| 1 | Column reinforcement | Level 4, grids C to F | Complete, inspected by consultant, OK to cast | 2026-11-02 | |
| 2 | Slab formwork | Level 4, east bay | About 70 percent done | 2026-11-02; crew held up 1 hour waiting for plywood | |
| 3 | Stair rebar | Stair S2 | Started | 2026-11-02 | |
| 4 | Blockwork | Level 2, grid A-C | In progress; masons moved to cleaning on 2026-11-04 due to block shortage | about 1800 blocks used | 2026-11-02 |
| 5 | Electrical sleeves | Listed 2026-11-02, no details | |||
| 6 | Cleaning and shifting materials | Helpers, 2026-11-02 | |||
| 7 | Slab concrete pour, C35 | Level 4, grids A to F | Completed | 42 m3 | 2026-11-04; finished 4:30pm; 6 cubes taken |
| 8 | Edge protection installation | Level 3, grid 4 | Installed | 2026-11-04 | |
| 9 | Site cleaning | 2026-11-04; masons redeployed due to block shortage | |||
| 10 | Rebar prefabrication | Ground level | 2026-11-05; crews redeployed during crane stoppage |
4. Materials received
| Description | Quantity | Remarks |
|---|---|---|
| Blocks | 2000 of 5000 delivered | Short delivery; still short on 2026-11-04 |
| Plywood sheets | 40 | Further sheets needed 2026-11-03 |
| Concrete C35 | 42 m3 | Placed in Level 4 slab; one truck waited 35 minutes, slump checked OK |
5. Issues and delays
| No. | Issue | Area / location | Severity | Action | Owner | Due |
|---|---|---|---|---|---|---|
| 1 | Short block delivery, 2000 of 5000; masons moved to cleaning | Level 2 blockwork | High | Procurement informed | ||
| 2 | Carpentry crew held up 1 hour waiting for plywood from the yard | Level 4, east bay | Medium | |||
| 3 | Work stopped due to missing edge protection | Level 3, grid 4 | High | Install barriers; reported installed 2026-11-04 | Carpentry crew | 2026-11-03 |
| 4 | Concrete pump breakdown, hydraulic hose failure, 40 minutes | Level 4 slab | Medium | Repaired by supplier mechanic | ||
| 5 | Concrete truck waited 35 minutes during pump breakdown | Level 4 slab | Low | Slump checked OK before placing | ||
| 6 | Tower crane stopped, wind over 45 km/h; about 3 hours lost | Level 5 columns; Level 3 formwork | High | Crews moved to ground level rebar prefabrication; work resumed at 12 |
6. Health and safety
| No. | Observation | Severity | Action | Owner |
|---|---|---|---|---|
| 1 | Missing edge protection, Level 3 grid 4, opening approx. 6 m | High | Work stopped; barriers installed, reported 2026-11-04 | Carpentry crew |
| 2 | Two workers on Level 2 scaffolding without safety harness | Medium | Workers brought down; verbal warning issued | |
| 3 | Temperature 38 degrees, heat stress risk | Low | Toolbox talk for 42 workers; extra water and shade provided |
7. Delay details
| Activity affected | Level 5 column rebar lifting and Level 3 formwork strip |
|---|---|
| Cause | Tower crane stopped as wind speed exceeded 45 km/h, as per the lifting plan |
| Started | 2026-11-05, 9am |
| Duration | 9am to 12 noon (about 3 hours) |
| Stated impact | About 3 hours lost for 18 steel fixers and 14 carpenters |
| Responsible | Not stated |
| Mitigation | Crews moved to ground level rebar prefabrication; work resumed at 12 |
| Notified | Consultant by email; client PM by phone |
| Reference | GW-0052 |
8. Open items register
| Ref. | Type | Description | Area / location | Severity | Owner | Due | Raised |
|---|---|---|---|---|---|---|---|
| A-0105 | Issue | Short block delivery, 2000 of 5000 arrived; masons stop on Wednesday unless balance arrives | Level 2 blockwork | High | GW-0044 | ||
| A-0106 | Issue | Carpentry crew held up 1 hour waiting for plywood from the yard | Level 4, east bay | Medium | GW-0045 | ||
| A-0107 | Issue | إيقاف العمل في منطقة الدور الثالث عند المحور 4 بسبب نقص حماية الحواف | الدور الثالث، المحور 4 | High | فريق النجارة | اليوم | GW-0046 |
| A-0108 | Safety | نقص حماية الحواف في الدور الثالث عند المحور 4، فتحة بطول 6 متر تقريباً, Action: إيقاف العمل في المنطقة وتركيب الحواجز اليوم | High | فريق النجارة | GW-0046 | ||
| A-0109 | Safety | عاملان يعملان على السقالة في الدور الثاني دون حزام أمان, Action: إنزال العاملين من السقالة وتوجيه إنذار شفهي لهما | Medium | GW-0046 | |||
| A-0110 | Safety | ارتفاع درجة الحرارة إلى 38 درجة وخطر الإجهاد الحراري, Action: توفير مياه وأماكن ظل إضافية | Low | GW-0046 | |||
| A-0111 | Issue | Concrete pump breakdown, hydraulic hose failure, 40 minutes; pour resumed after supplier mechanic repair | Level 4 slab | Medium | GW-0047 | ||
| A-0112 | Issue | Concrete truck waited 35 minutes during pump breakdown; slump checked OK before placing | Level 4 slab | Low | GW-0047 | ||
| A-0113 | Issue | Block shortage: only 2000 of 5000 delivered; masons moved to cleaning | High | GW-0047 | |||
| A-0114 | Safety | Edge protection on Level 3, grid 4 now installed, Action: Installed | Low | GW-0047 | |||
| A-0126 | Issue | Tower crane stopped due to wind speed over 45 km/h, per lifting plan; about 3 hours lost | Level 5 columns; Level 3 formwork | High | GW-0052 | ||
| A-0127 | Delay | Level 5 column rebar lifting and Level 3 formwork strip, Tower crane stopped as wind speed exceeded 45 km/h, as per the lifting plan, 9am to 12 noon (about 3 hours) | High | GW-0052 |
9. Decisions needed
| No. | Decision | Owner |
|---|---|---|
| 1 | Consultant approval to cast Level 4 columns, grids C to F | Consultant |
10. Planned for next week
| No. | Action |
|---|---|
| 1 | Curing of Level 4 slab |
| 2 | Strike Level 3 soffit formwork |
| 3 | Start Level 5 column rebar |
11. Sign-off