Weekly Progress Report

Level 4 slab poured, block shortage and crane wind stoppage

Report no.GW-0053
Rev.0
StatusDraft for review
ProjectAl Noor Tower
LocationKing Fahd Road, Riyadh
Contract no.C-0412
ClientAl Noor Real Estate Development
ConsultantRiyadh Engineering Consultants
ContractorNajd Contracting
CompanyNajd Contracting
Date02 Nov 2026 – 08 Nov 2026
Prepared bySara Al-Qahtani
RoleNot stated
Based on5 daily reports

1. Summary

Level 4 column reinforcement, grids C to F, was completed and approved by the consultant for casting, and the Level 4 slab was poured between grids A to F with 42 m3 of C35 on 2026-11-04. The concrete pump broke down for 40 minutes during the pour due to a hydraulic hose failure and was repaired by the supplier mechanic. Block delivery remained short at 2000 of 5000, and masons were moved to site cleaning on 2026-11-04. HSE reported missing edge protection on Level 3 at grid 4, which was installed by 2026-11-04, and two workers on Level 2 scaffolding without safety harnesses. On 2026-11-05 the tower crane was stopped from 9am to 12 noon due to high wind, with about 3 hours lost for steel fixers and carpenters.

2. Site diary

DateReportManpowerWeatherIssues and delays
02 Nov 2026GW-0044 Level 4 columns and slab formwork, Level 2 blockwork48Hot and clear, about 37 degrees, light wind in the morning1
02 Nov 2026GW-0045 Level 4 slab formwork, column and stair rebar, Level 2 blockwork46Partly cloudy, high 35°C, low 25°C, wind up to 9 km/h, no rain (Open-Meteo)1
03 Nov 2026GW-0046 ملاحظات السلامة: نقص حماية الحواف في الدور الثالث والعمل دون حزام أمان في الدور الثانيحار جداً، درجة الحرارة 38 درجة4
04 Nov 2026GW-0047 Level 4 slab pour, grids A to F52Hot, 36 degrees4
05 Nov 2026GW-0052 Tower crane stoppage due to high wind32Wind speed over 45 km/h from 9am to 12 noon1

3. Work carried out

No.ActivityArea / locationStatusQuantityRemarks
1Column reinforcementLevel 4, grids C to FComplete, inspected by consultant, OK to cast2026-11-02
2Slab formworkLevel 4, east bayAbout 70 percent done2026-11-02; crew held up 1 hour waiting for plywood
3Stair rebarStair S2Started2026-11-02
4BlockworkLevel 2, grid A-CIn progress; masons moved to cleaning on 2026-11-04 due to block shortageabout 1800 blocks used2026-11-02
5Electrical sleevesListed 2026-11-02, no details
6Cleaning and shifting materialsHelpers, 2026-11-02
7Slab concrete pour, C35Level 4, grids A to FCompleted42 m32026-11-04; finished 4:30pm; 6 cubes taken
8Edge protection installationLevel 3, grid 4Installed2026-11-04
9Site cleaning2026-11-04; masons redeployed due to block shortage
10Rebar prefabricationGround level2026-11-05; crews redeployed during crane stoppage

4. Materials received

DescriptionQuantityRemarks
Blocks2000 of 5000 deliveredShort delivery; still short on 2026-11-04
Plywood sheets40Further sheets needed 2026-11-03
Concrete C3542 m3Placed in Level 4 slab; one truck waited 35 minutes, slump checked OK

5. Issues and delays

No.IssueArea / locationSeverityActionOwnerDue
1Short block delivery, 2000 of 5000; masons moved to cleaningLevel 2 blockworkHighProcurement informed
2Carpentry crew held up 1 hour waiting for plywood from the yardLevel 4, east bayMedium
3Work stopped due to missing edge protectionLevel 3, grid 4HighInstall barriers; reported installed 2026-11-04Carpentry crew2026-11-03
4Concrete pump breakdown, hydraulic hose failure, 40 minutesLevel 4 slabMediumRepaired by supplier mechanic
5Concrete truck waited 35 minutes during pump breakdownLevel 4 slabLowSlump checked OK before placing
6Tower crane stopped, wind over 45 km/h; about 3 hours lostLevel 5 columns; Level 3 formworkHighCrews moved to ground level rebar prefabrication; work resumed at 12

6. Health and safety

No.ObservationSeverityActionOwner
1Missing edge protection, Level 3 grid 4, opening approx. 6 mHighWork stopped; barriers installed, reported 2026-11-04Carpentry crew
2Two workers on Level 2 scaffolding without safety harnessMediumWorkers brought down; verbal warning issued
3Temperature 38 degrees, heat stress riskLowToolbox talk for 42 workers; extra water and shade provided

7. Delay details

Activity affectedLevel 5 column rebar lifting and Level 3 formwork strip
CauseTower crane stopped as wind speed exceeded 45 km/h, as per the lifting plan
Started2026-11-05, 9am
Duration9am to 12 noon (about 3 hours)
Stated impactAbout 3 hours lost for 18 steel fixers and 14 carpenters
ResponsibleNot stated
MitigationCrews moved to ground level rebar prefabrication; work resumed at 12
NotifiedConsultant by email; client PM by phone
ReferenceGW-0052

8. Open items register

Ref.TypeDescriptionArea / locationSeverityOwnerDueRaised
A-0105IssueShort block delivery, 2000 of 5000 arrived; masons stop on Wednesday unless balance arrivesLevel 2 blockworkHighGW-0044
A-0106IssueCarpentry crew held up 1 hour waiting for plywood from the yardLevel 4, east bayMediumGW-0045
A-0107Issueإيقاف العمل في منطقة الدور الثالث عند المحور 4 بسبب نقص حماية الحوافالدور الثالث، المحور 4Highفريق النجارةاليومGW-0046
A-0108Safetyنقص حماية الحواف في الدور الثالث عند المحور 4، فتحة بطول 6 متر تقريباً, Action: إيقاف العمل في المنطقة وتركيب الحواجز اليومHighفريق النجارةGW-0046
A-0109Safetyعاملان يعملان على السقالة في الدور الثاني دون حزام أمان, Action: إنزال العاملين من السقالة وتوجيه إنذار شفهي لهماMediumGW-0046
A-0110Safetyارتفاع درجة الحرارة إلى 38 درجة وخطر الإجهاد الحراري, Action: توفير مياه وأماكن ظل إضافيةLowGW-0046
A-0111IssueConcrete pump breakdown, hydraulic hose failure, 40 minutes; pour resumed after supplier mechanic repairLevel 4 slabMediumGW-0047
A-0112IssueConcrete truck waited 35 minutes during pump breakdown; slump checked OK before placingLevel 4 slabLowGW-0047
A-0113IssueBlock shortage: only 2000 of 5000 delivered; masons moved to cleaningHighGW-0047
A-0114SafetyEdge protection on Level 3, grid 4 now installed, Action: InstalledLowGW-0047
A-0126IssueTower crane stopped due to wind speed over 45 km/h, per lifting plan; about 3 hours lostLevel 5 columns; Level 3 formworkHighGW-0052
A-0127DelayLevel 5 column rebar lifting and Level 3 formwork strip, Tower crane stopped as wind speed exceeded 45 km/h, as per the lifting plan, 9am to 12 noon (about 3 hours)HighGW-0052

9. Decisions needed

No.DecisionOwner
1Consultant approval to cast Level 4 columns, grids C to FConsultant

10. Planned for next week

No.Action
1Curing of Level 4 slab
2Strike Level 3 soffit formwork
3Start Level 5 column rebar

11. Sign-off

Prepared by
NameSara Al-Qahtani
Signature
Date
Reviewed by (Project Director)
Name
Signature
Date
Received by (Consultant)
Name
Signature
Date

Written by Groundwork from the sender's own notes. Not valid until reviewed and signed.