Snag List

Snag walkthrough, Villas 3 and 4

Report no.GW-0051
Rev.0
StatusDraft for review
ProjectQurtubah Villas Phase 2
LocationQurtubah, Riyadh
Contract no.C-0438
ClientQurtubah Homes
ConsultantAl Mimar Consultants
ContractorNajd Contracting
CompanyNajd Contracting
DateThursday 5 Nov
AttendeesClient representative
Prepared byYusuf Rahman
RoleSite Engineer
Based on3 messages

1. Summary

A snag walkthrough of Villas 3 and 4 was carried out with the client representative on Thursday 5 Nov. Six defects were recorded across the two villas. High priority items are out-of-plumb plaster to the stair wall in Villa 3 and a water stain on the roof slab soffit above the stair in Villa 4, where waterproofing is to be checked.

2. Snag list

No.Area / locationDefectTradePriorityResponsible
1Villa 3, stair wallPlaster out of plumb, approx. 15mmPlasteringHighPlasterers
2Villa 3, master bedroomWindow frame scratchedAluminiumMediumAluminium subcontractor
3Villa 3, kitchen, near doorFloor tile crackedTilingMediumTiling
4Villa 4, living roomTwo electrical boxes looseElectricalLowElectrician
5Villa 4, guest toiletDoor does not close fullyCarpentryMediumCarpenter
6Villa 4, roof slab soffit above stairWater stain; waterproofing to be checkedWaterproofingHigh

3. Next steps

No.Action
1Check waterproofing above Villa 4 stair

4. Sign-off

Prepared by (Site Engineer)
NameYusuf Rahman
Signature
Date
Accepted by (Contractor)
Name
Signature
Date
Verified by (Consultant)
Name
Signature
Date

Appendix A: notes as received

Message 1, 05 Nov 2026, 15:17

Snag walkthrough villas 3 and 4 with the client rep, Thursday 5 Nov.

Message 2, 05 Nov 2026, 15:18

Villa 3: stair wall plaster out of plumb about 15mm, high priority, plasterers. Master bedroom window frame scratched, medium, aluminium sub. Kitchen floor tile cracked near the door, medium, tiling.

Message 3, 05 Nov 2026, 15:19

Villa 4: two electrical boxes loose in the living room, low, electrician. Guest toilet door does not close fully, medium, carpenter. Water stain on the roof slab soffit above the stair, high, check waterproofing.

Written by Groundwork from the sender's own notes. Not valid until reviewed and signed.