Site Visit Report

Villa 7 roof slab pour, Villa 9 waterproofing rework and Villa 3 plaster

Report no.GW-0050
Rev.0
StatusDraft for review
ProjectQurtubah Villas Phase 2
LocationQurtubah, Riyadh
Contract no.C-0438
ClientQurtubah Homes
ConsultantAl Mimar Consultants
ContractorNajd Contracting
CompanyNajd Contracting
Date4 Nov
Working hours10am to 12pm
AttendeesOmar Siddiqui (consultant), Yusuf Rahman (contractor site engineer), Mohammed Al-Qahtani (QA/QC)
Prepared byOmar Siddiqui
RoleConsultant Engineer
Based on4 messages

1. Summary

The consultant visited Qurtubah Villas Phase 2 on 4 Nov from 10am to 12pm. The Villa 7 roof slab pour was observed, with acceptable vibration and curing. Waterproofing rework at Villa 9 is in progress under NCR-031 and requires re-inspection before backfilling. The stair wall plaster at Villa 3 is out of plumb by about 15 mm and is to be corrected before paint. Instructions were issued for an updated 3 week look-ahead and for shade and water stations at each villa cluster because of heat.

2. Observations

No.ElementFindingResultAction
1Villa 7 roof slab pourVibration and curing acceptablepass
2Villa 9 waterproofingRework in progress per NCR-031observationRe-inspection required before backfilling
3Villa 3 stair wall plasterOut of plumb by about 15 mmfailCorrect before paint

3. Instructions received and issued

No.FromInstruction
1ConsultantContractor to submit updated 3 week look-ahead by Sunday
2ConsultantContractor to provide shade and water stations at each villa cluster because of heat

4. Health and safety

No.ObservationSeverityActionOwner
1Heat exposure; shade and water stations required at each villa clusterMediumProvide shade and water stations at each villa clusterContractor

5. Follow-up actions

No.Action
1Contractor to submit updated 3 week look-ahead by Sunday
2Contractor to provide shade and water stations at each villa cluster
3Re-inspect Villa 9 waterproofing before backfilling
4Correct Villa 3 stair wall plaster before paint

6. Work carried out

No.ActivityArea / locationStatusRemarks
1Roof slab pourVilla 7Vibration and curing acceptable
2Waterproofing reworkVilla 9In progressPer NCR-031

7. Sign-off

Prepared by (Consultant Engineer)
NameOmar Siddiqui
Signature
Date
Issued to (Contractor)
Name
Signature
Date
Copy to (Client)
Name
Signature
Date

Appendix A: notes as received

Message 1, 04 Nov 2026, 12:11

Consultant site visit, Qurtubah Villas Phase 2, 4 Nov, 10am to 12pm. Attended: Omar Siddiqui (consultant), Yusuf Rahman (contractor site engineer), Mohammed Al-Qahtani (QA/QC).

Message 2, 04 Nov 2026, 12:12

Observed villa 7 roof slab pour, vibration and curing acceptable. Villa 9 waterproofing rework in progress per NCR-031, re-inspection required before backfilling.

Message 3, 04 Nov 2026, 12:13

Instruction issued: contractor to submit updated 3 week look-ahead by Sunday, and to provide shade and water stations at each villa cluster because of heat.

Message 4, 04 Nov 2026, 12:14

Villa 3 plaster on the stair wall is out of plumb by about 15 mm, to be corrected before paint.