Villa 7 roof slab pour, Villa 9 waterproofing rework and Villa 3 plaster
1. Summary
The consultant visited Qurtubah Villas Phase 2 on 4 Nov from 10am to 12pm. The Villa 7 roof slab pour was observed, with acceptable vibration and curing. Waterproofing rework at Villa 9 is in progress under NCR-031 and requires re-inspection before backfilling. The stair wall plaster at Villa 3 is out of plumb by about 15 mm and is to be corrected before paint. Instructions were issued for an updated 3 week look-ahead and for shade and water stations at each villa cluster because of heat.
2. Observations
| No. | Element | Finding | Result | Action |
|---|---|---|---|---|
| 1 | Villa 7 roof slab pour | Vibration and curing acceptable | pass | |
| 2 | Villa 9 waterproofing | Rework in progress per NCR-031 | observation | Re-inspection required before backfilling |
| 3 | Villa 3 stair wall plaster | Out of plumb by about 15 mm | fail | Correct before paint |
3. Instructions received and issued
| No. | From | Instruction |
|---|---|---|
| 1 | Consultant | Contractor to submit updated 3 week look-ahead by Sunday |
| 2 | Consultant | Contractor to provide shade and water stations at each villa cluster because of heat |
4. Health and safety
| No. | Observation | Severity | Action | Owner |
|---|---|---|---|---|
| 1 | Heat exposure; shade and water stations required at each villa cluster | Medium | Provide shade and water stations at each villa cluster | Contractor |
5. Follow-up actions
| No. | Action |
|---|---|
| 1 | Contractor to submit updated 3 week look-ahead by Sunday |
| 2 | Contractor to provide shade and water stations at each villa cluster |
| 3 | Re-inspect Villa 9 waterproofing before backfilling |
| 4 | Correct Villa 3 stair wall plaster before paint |
6. Work carried out
| No. | Activity | Area / location | Status | Remarks |
|---|---|---|---|---|
| 1 | Roof slab pour | Villa 7 | Vibration and curing acceptable | |
| 2 | Waterproofing rework | Villa 9 | In progress | Per NCR-031 |
7. Sign-off
Appendix A: notes as received
Consultant site visit, Qurtubah Villas Phase 2, 4 Nov, 10am to 12pm. Attended: Omar Siddiqui (consultant), Yusuf Rahman (contractor site engineer), Mohammed Al-Qahtani (QA/QC).
Observed villa 7 roof slab pour, vibration and curing acceptable. Villa 9 waterproofing rework in progress per NCR-031, re-inspection required before backfilling.
Instruction issued: contractor to submit updated 3 week look-ahead by Sunday, and to provide shade and water stations at each villa cluster because of heat.
Villa 3 plaster on the stair wall is out of plumb by about 15 mm, to be corrected before paint.