Villa 7 roof slab pour, blockwork, plastering and Villa 9 waterproofing rework
1. Summary
The Villa 7 first floor roof slab was poured (28 m3). Villa 8 first floor blockwork is reported 60% done, and internal plastering at Villas 3 and 4 is about 80%. Waterproofing rework started at Villa 9 following NCR-031. The water tanker arrived 2 hours late in the morning, which delayed curing at Villa 6.
2. Work carried out
| No. | Activity | Area / location | Status | Quantity | Remarks |
|---|---|---|---|---|---|
| 1 | First floor roof slab concrete pour | Villa 7 | Poured | 28 m3 | |
| 2 | First floor blockwork | Villa 8 | 60% done | ||
| 3 | Internal plastering | Villas 3 and 4 | About 80% | ||
| 4 | Waterproofing rework, roll laps being redone | Villa 9 | Started | Following NCR-031 | |
| 5 | Curing | Villa 6 | Delayed | Water tanker 2 hours late |
3. Manpower
| Trade | No. |
|---|---|
| Masons | 10 |
| Plasterers | 12 |
| Steel fixers | 8 |
| Helpers | 7 |
| Total | 37 |
4. Plant and equipment
| Description | No. | Condition |
|---|---|---|
| Mobile crane | Half day | |
| Mixer | 1 |
5. Materials received
Not reported in the notes.
6. Inspections, RFIs and NCRs
| Reference | Element | Remarks |
|---|---|---|
| NCR-031 | Villa 9 waterproofing | Rework started, roll laps being redone |
7. Issues and delays
| No. | Issue | Area / location | Severity |
|---|---|---|---|
| 1 | Water tanker arrived 2 hours late in the morning, curing delayed | Villa 6 | Medium |
8. Health and safety
Not reported in the notes.
9. Planned for next working day
Not reported in the notes.
10. Sign-off
Appendix A: notes as received
Qurtubah Villas daily, Wed 4 Nov. Clear, 35 degrees. 6:30am to 4pm.
Villa 7 first floor roof slab poured, 28 m3. Villa 8 blockwork first floor 60% done. Villas 3 and 4 plastering internal, about 80%.
Villa 9 waterproofing rework started after NCR-031, roll laps being redone.
Manpower 37: 10 masons, 12 plasterers, 8 steel fixers, 7 helpers. Plant: mobile crane half day, 1 mixer.
Water tanker late 2 hours in the morning, curing on villa 6 delayed.
Written by Groundwork from the sender's own notes. Not valid until reviewed and signed.