Daily Site Report

Villa 7 roof slab pour, blockwork, plastering and Villa 9 waterproofing rework

Report no.GW-0049
Rev.0
StatusDraft for review
ProjectQurtubah Villas Phase 2
LocationQurtubah, Riyadh
Contract no.C-0438
ClientQurtubah Homes
ConsultantAl Mimar Consultants
ContractorNajd Contracting
CompanyNajd Contracting
DateWed 4 Nov
WeatherClear, 35 degrees
Working hours6:30am to 4pm
Prepared byYusuf Rahman
RoleSite Engineer
Based on5 messages

1. Summary

The Villa 7 first floor roof slab was poured (28 m3). Villa 8 first floor blockwork is reported 60% done, and internal plastering at Villas 3 and 4 is about 80%. Waterproofing rework started at Villa 9 following NCR-031. The water tanker arrived 2 hours late in the morning, which delayed curing at Villa 6.

2. Work carried out

No.ActivityArea / locationStatusQuantityRemarks
1First floor roof slab concrete pourVilla 7Poured28 m3
2First floor blockworkVilla 860% done
3Internal plasteringVillas 3 and 4About 80%
4Waterproofing rework, roll laps being redoneVilla 9StartedFollowing NCR-031
5CuringVilla 6DelayedWater tanker 2 hours late

3. Manpower

TradeNo.
Masons10
Plasterers12
Steel fixers8
Helpers7
Total37

4. Plant and equipment

DescriptionNo.Condition
Mobile craneHalf day
Mixer1

5. Materials received

Not reported in the notes.

6. Inspections, RFIs and NCRs

ReferenceElementRemarks
NCR-031Villa 9 waterproofingRework started, roll laps being redone

7. Issues and delays

No.IssueArea / locationSeverity
1Water tanker arrived 2 hours late in the morning, curing delayedVilla 6Medium

8. Health and safety

Not reported in the notes.

9. Planned for next working day

Not reported in the notes.

10. Sign-off

Prepared by (Site Engineer)
NameYusuf Rahman
Signature
Date
Reviewed by (Project Manager)
Name
Signature
Date
Received by (Consultant)
Name
Signature
Date

Appendix A: notes as received

Message 1, 04 Nov 2026, 16:25

Qurtubah Villas daily, Wed 4 Nov. Clear, 35 degrees. 6:30am to 4pm.

Message 2, 04 Nov 2026, 16:26

Villa 7 first floor roof slab poured, 28 m3. Villa 8 blockwork first floor 60% done. Villas 3 and 4 plastering internal, about 80%.

Message 3, 04 Nov 2026, 16:27

Villa 9 waterproofing rework started after NCR-031, roll laps being redone.

Message 4, 04 Nov 2026, 16:28

Manpower 37: 10 masons, 12 plasterers, 8 steel fixers, 7 helpers. Plant: mobile crane half day, 1 mixer.

Message 5, 04 Nov 2026, 16:29

Water tanker late 2 hours in the morning, curing on villa 6 delayed.

Written by Groundwork from the sender's own notes. Not valid until reviewed and signed.