Level 4 slab pour, grids A to F
1. Summary
The Level 4 slab was poured between grids A to F, 42 m3 of C35, finishing at 4:30pm, and 6 cubes were taken. The concrete pump broke down at 11am for 40 minutes due to a hydraulic hose. A supplier mechanic repaired it, and one truck waited 35 minutes with slump checked OK before placing. Blocks remain short, with only 2000 of 5000 delivered, so masons were moved to cleaning.
2. Work carried out
| No. | Activity | Area / location | Status | Quantity | Remarks |
|---|---|---|---|---|---|
| 1 | Slab concrete pour, C35 | Level 4, grids A to F | Completed | 42 m3 | Finished at 4:30pm; 6 cubes taken |
| 2 | Edge protection installation | Level 3, grid 4 | Installed | ||
| 3 | Site cleaning | Masons redeployed due to block shortage |
3. Manpower
| Trade | No. |
|---|---|
| Total workforce | 52 |
| Total | 52 |
4. Plant and equipment
| Description | Condition |
|---|---|
| Concrete pump | Broke down at 11am for 40 minutes (hydraulic hose); repaired by supplier mechanic, working after |
5. Materials received
| Description | Quantity | Remarks |
|---|---|---|
| Concrete C35 | 42 m3 | Placed in Level 4 slab; one truck waited 35 minutes, slump checked OK before placing |
| Blocks | 2000 of 5000 delivered | Short |
6. Issues and delays
| No. | Issue | Area / location | Severity | Action |
|---|---|---|---|---|
| 1 | Concrete pump breakdown, hydraulic hose failure, 40 minutes; pour resumed after supplier mechanic repair | Level 4 slab | Medium | Repaired by supplier mechanic |
| 2 | Concrete truck waited 35 minutes during pump breakdown; slump checked OK before placing | Level 4 slab | Low | Slump test carried out before placing |
| 3 | Block shortage: only 2000 of 5000 delivered; masons moved to cleaning | High |
7. Health and safety
| No. | Observation | Severity | Action |
|---|---|---|---|
| 1 | Edge protection on Level 3, grid 4 now installed | Low | Installed |
8. Planned for next working day
| No. | Action |
|---|---|
| 1 | Curing of Level 4 slab |
| 2 | Strike Level 3 soffit formwork |
| 3 | Start Level 5 column rebar |
9. Sign-off
Appendix A: notes as received
Daily report Al Noor, Wednesday 4 Nov. Hot, 36 degrees. Hours 5am to 5pm because of the pour.
Level 4 slab poured, grids A to F, 42 m3 of C35, finished at 4:30pm. Cubes taken, 6 cubes.
Concrete pump broke down at 11am for 40 minutes, hydraulic hose. Supplier sent a mechanic, pour continued after. One truck waited 35 minutes, slump checked OK before placing.
Manpower 52 total. Blocks still short, only 2000 of 5000 delivered, masons moved to cleaning. Edge protection on level 3 grid 4 now installed.
Tomorrow: curing level 4, strike level 3 soffit formwork, start level 5 column rebar.
Written by Groundwork from the sender's own notes. Not valid until reviewed and signed.