Daily Site Report

Level 4 slab pour, grids A to F

Report no.GW-0047
Rev.0
StatusDraft for review
ProjectAl Noor Tower
LocationKing Fahd Road, Riyadh
Contract no.C-0412
ClientAl Noor Real Estate Development
ConsultantRiyadh Engineering Consultants
ContractorNajd Contracting
CompanyNajd Contracting
DateWednesday 4 Nov
WeatherHot, 36 degrees
Working hours5am to 5pm (extended for the pour)
Prepared byAhmed Al-Harbi
RoleSite Engineer
Based on5 messages

1. Summary

The Level 4 slab was poured between grids A to F, 42 m3 of C35, finishing at 4:30pm, and 6 cubes were taken. The concrete pump broke down at 11am for 40 minutes due to a hydraulic hose. A supplier mechanic repaired it, and one truck waited 35 minutes with slump checked OK before placing. Blocks remain short, with only 2000 of 5000 delivered, so masons were moved to cleaning.

2. Work carried out

No.ActivityArea / locationStatusQuantityRemarks
1Slab concrete pour, C35Level 4, grids A to FCompleted42 m3Finished at 4:30pm; 6 cubes taken
2Edge protection installationLevel 3, grid 4Installed
3Site cleaningMasons redeployed due to block shortage

3. Manpower

TradeNo.
Total workforce52
Total52

4. Plant and equipment

DescriptionCondition
Concrete pumpBroke down at 11am for 40 minutes (hydraulic hose); repaired by supplier mechanic, working after

5. Materials received

DescriptionQuantityRemarks
Concrete C3542 m3Placed in Level 4 slab; one truck waited 35 minutes, slump checked OK before placing
Blocks2000 of 5000 deliveredShort

6. Issues and delays

No.IssueArea / locationSeverityAction
1Concrete pump breakdown, hydraulic hose failure, 40 minutes; pour resumed after supplier mechanic repairLevel 4 slabMediumRepaired by supplier mechanic
2Concrete truck waited 35 minutes during pump breakdown; slump checked OK before placingLevel 4 slabLowSlump test carried out before placing
3Block shortage: only 2000 of 5000 delivered; masons moved to cleaningHigh

7. Health and safety

No.ObservationSeverityAction
1Edge protection on Level 3, grid 4 now installedLowInstalled

8. Planned for next working day

No.Action
1Curing of Level 4 slab
2Strike Level 3 soffit formwork
3Start Level 5 column rebar

9. Sign-off

Prepared by (Site Engineer)
NameAhmed Al-Harbi
Signature
Date
Reviewed by (Project Manager)
Name
Signature
Date
Received by (Consultant)
Name
Signature
Date

Appendix A: notes as received

Message 1, 04 Nov 2026, 17:00

Daily report Al Noor, Wednesday 4 Nov. Hot, 36 degrees. Hours 5am to 5pm because of the pour.

Message 2, 04 Nov 2026, 17:01

Level 4 slab poured, grids A to F, 42 m3 of C35, finished at 4:30pm. Cubes taken, 6 cubes.

Message 3, 04 Nov 2026, 17:02

Concrete pump broke down at 11am for 40 minutes, hydraulic hose. Supplier sent a mechanic, pour continued after. One truck waited 35 minutes, slump checked OK before placing.

Message 4, 04 Nov 2026, 17:03

Manpower 52 total. Blocks still short, only 2000 of 5000 delivered, masons moved to cleaning. Edge protection on level 3 grid 4 now installed.

Message 5, 04 Nov 2026, 17:04

Tomorrow: curing level 4, strike level 3 soffit formwork, start level 5 column rebar.

Written by Groundwork from the sender's own notes. Not valid until reviewed and signed.