Level 3 slab pour and column rebar
1. Summary
Level 3 slab zone B was poured with 42 cubic metres of C35 concrete, completed around 2 o'clock. Rebar work for level 3 columns in zone C is about half complete. A short delivery of concrete blocks may halt masonry work tomorrow, and two workers were observed without harnesses pending edge protection installation.
2. Work carried out
| No. | Activity | Area / location | Status | Quantity |
|---|---|---|---|---|
| 1 | Concrete pour | Level 3 slab zone B | finished | 42 cubic metres of C35 |
| 2 | Rebar fixing | Level 3 columns zone C | in progress | about half done |
3. Manpower
| Company | Trade | No. |
|---|---|---|
| Al Rashid | steel fixers | 18 |
| Al Rashid | carpenters | 12 |
| Al Rashid | labourers | 6 |
| Total | 36 |
4. Plant and equipment
| Description | No. | Condition |
|---|---|---|
| tower crane | 1 | working |
| concrete pump | 1 | working |
| concrete pump | 1 | broken |
5. Materials received
| Description | Quantity | Supplier | Remarks |
|---|---|---|---|
| 16mm rebar | 12 tonnes | Rajhi Steel | delivered |
| concrete blocks | 2000 (short of 5000) | short |
6. Inspections, RFIs and NCRs
| Reference | Element | Result | Remarks |
|---|---|---|---|
| RFI 112 | Level 3 slab rebar | approved | Consultant inspected this morning |
7. Issues and delays
| No. | Issue | Severity | Action |
|---|---|---|---|
| 1 | Concrete block delivery short, may stop masons tomorrow | High | Supplier to deliver remaining blocks |
8. Health and safety
| No. | Observation | Severity | Action | Owner |
|---|---|---|---|---|
| 1 | Two workers at level 3 edge without harness | High | Safety officer Ahmed to install edge protection by tomorrow morning | Ahmed |
9. Planned for next working day
| No. | Action |
|---|---|
| 1 | Finish column rebar and start formwork in zone C tomorrow |
| 2 | Edge protection to be installed by tomorrow morning |
10. Photographic record
11. Sign-off
Appendix A: notes as received
Today's update for Al Noor Tower, Riyadh. Working 7am to 5pm, hot, about 39 degrees. Poured level 3 slab zone B, 42 cubic metres of C35, finished around 2 o'clock. Rebar for level 3 columns zone C about half done. 18 steel fixers, 12 carpenters from Al Rashid subcontractor, 6 labourers. One tower crane, one concrete pump working, second pump broken. Received 12 tonnes of 16mm rebar from Rajhi Steel. Consultant inspected level 3 slab rebar this morning under RFI 112, approved. Block delivery short, 2000 instead of 5000, masons stop tomorrow unless supplier delivers. Two workers at level 3 edge without harness, told safety officer Ahmed to fix edge protection by tomorrow morning. Tomorrow we finish column rebar and start formwork in zone C.
Written by Groundwork from the sender's own notes. Not valid until reviewed and signed.