Daily Site Report

Level 3 slab pour and column rebar

Report no.GW-0008
Rev.0
StatusDraft for review
ProjectAl Noor Tower
LocationRiyadh
CompanyBinyan Contracting
DateSunday, 08 Nov 2026
Weatherhot, about 39 degrees
Working hours7am to 5pm
Prepared byKhalid Rahman
RoleSite Engineer
Based on1 photo · 1 message

1. Summary

Level 3 slab zone B was poured with 42 cubic metres of C35 concrete, completed around 2 o'clock. Rebar work for level 3 columns in zone C is about half complete. A short delivery of concrete blocks may halt masonry work tomorrow, and two workers were observed without harnesses pending edge protection installation.

2. Work carried out

No.ActivityArea / locationStatusQuantity
1Concrete pourLevel 3 slab zone Bfinished42 cubic metres of C35
2Rebar fixingLevel 3 columns zone Cin progressabout half done

3. Manpower

CompanyTradeNo.
Al Rashidsteel fixers18
Al Rashidcarpenters12
Al Rashidlabourers6
Total36

4. Plant and equipment

DescriptionNo.Condition
tower crane1working
concrete pump1working
concrete pump1broken

5. Materials received

DescriptionQuantitySupplierRemarks
16mm rebar12 tonnesRajhi Steeldelivered
concrete blocks2000 (short of 5000)short

6. Inspections, RFIs and NCRs

ReferenceElementResultRemarks
RFI 112Level 3 slab rebarapprovedConsultant inspected this morning

7. Issues and delays

No.IssueSeverityAction
1Concrete block delivery short, may stop masons tomorrowHighSupplier to deliver remaining blocks

8. Health and safety

No.ObservationSeverityActionOwner
1Two workers at level 3 edge without harnessHighSafety officer Ahmed to install edge protection by tomorrow morningAhmed

9. Planned for next working day

No.Action
1Finish column rebar and start formwork in zone C tomorrow
2Edge protection to be installed by tomorrow morning

10. Photographic record

Photo 1. High-angle view showing concrete pump boom over excavation, worker on walkway, rebar grid on floor, truck cab, tag 'BLACK C'
Photo 108 Nov 2026, 14:20
High-angle view showing concrete pump boom over excavation, worker on walkway, rebar grid on floor, truck cab, tag 'BLACK C'

11. Sign-off

Prepared by (Site Engineer)
NameKhalid Rahman
Signature
Date
Reviewed by (Project Manager)
Name
Signature
Date
Received by (Consultant)
Name
Signature
Date

Appendix A: notes as received

Message 1, 08 Nov 2026, 14:20

Today's update for Al Noor Tower, Riyadh. Working 7am to 5pm, hot, about 39 degrees. Poured level 3 slab zone B, 42 cubic metres of C35, finished around 2 o'clock. Rebar for level 3 columns zone C about half done. 18 steel fixers, 12 carpenters from Al Rashid subcontractor, 6 labourers. One tower crane, one concrete pump working, second pump broken. Received 12 tonnes of 16mm rebar from Rajhi Steel. Consultant inspected level 3 slab rebar this morning under RFI 112, approved. Block delivery short, 2000 instead of 5000, masons stop tomorrow unless supplier delivers. Two workers at level 3 edge without harness, told safety officer Ahmed to fix edge protection by tomorrow morning. Tomorrow we finish column rebar and start formwork in zone C.

Written by Groundwork from the sender's own notes. Not valid until reviewed and signed.