Tower crane stoppage due to high wind
1. Summary
The tower crane was stopped from 9am to 12 noon because wind speed exceeded 45 km/h, in accordance with the lifting plan. Level 5 column rebar lifting and Level 3 formwork stripping were affected, with about 3 hours lost for 18 steel fixers and 14 carpenters. Crews were moved to ground level rebar prefabrication and work resumed at 12. The consultant was informed by email and the client PM by phone.
2. Delay details
| Activity affected | Level 5 column rebar lifting and Level 3 formwork strip |
|---|---|
| Cause | Tower crane stopped as wind speed exceeded 45 km/h, as per the lifting plan |
| Started | 9am |
| Duration | 9am to 12 noon (about 3 hours) |
| Stated impact | About 3 hours lost for 18 steel fixers and 14 carpenters |
| Responsible | Not stated |
| Mitigation | Crews moved to ground level rebar prefabrication; work resumed at 12 |
| Notified | Consultant by email; client PM by phone |
| Reference | Not stated |
3. Work carried out
| No. | Activity | Area / location | Remarks |
|---|---|---|---|
| 1 | Rebar prefabrication (crews redeployed during crane stoppage) | Ground level | Mitigation during crane stoppage |
4. Issues and delays
| No. | Issue | Area / location | Severity | Action |
|---|---|---|---|---|
| 1 | Tower crane stopped due to wind speed over 45 km/h, per lifting plan; about 3 hours lost | Level 5 columns; Level 3 formwork | High | Crews moved to ground level rebar prefabrication; work resumed at 12 |
5. Mitigation and next steps
Not reported in the notes.
6. Manpower
| Trade | No. |
|---|---|
| Steel fixers | 18 |
| Carpenters | 14 |
| Total | 32 |
7. Plant and equipment
| Description | Condition |
|---|---|
| Tower crane | Stopped 9am to 12 noon due to high wind; resumed at 12 |
8. Sign-off
Appendix A: notes as received
Delay notice Al Noor Tower, Thursday 5 Nov. Tower crane stopped from 9am to 12 noon because wind speed went over 45 km/h, as per the lifting plan.
Activity affected: level 5 column rebar lifting and level 3 formwork strip. About 3 hours lost for 18 steel fixers and 14 carpenters.
Mitigation: crews moved to ground level rebar prefabrication. Work resumed at 12. Consultant informed by email, client PM informed by phone.
Written by Groundwork from the sender's own notes. Not valid until reviewed and signed.