Delay Notice

Tower crane stoppage due to high wind

Report no.GW-0052
Rev.0
StatusDraft for review
ProjectAl Noor Tower
LocationKing Fahd Road, Riyadh
Contract no.C-0412
ClientAl Noor Real Estate Development
ConsultantRiyadh Engineering Consultants
ContractorNajd Contracting
CompanyNajd Contracting
DateThursday 5 Nov
WeatherWind speed over 45 km/h from 9am to 12 noon
Prepared byAhmed Al-Harbi
RoleSite Engineer
Based on3 messages

1. Summary

The tower crane was stopped from 9am to 12 noon because wind speed exceeded 45 km/h, in accordance with the lifting plan. Level 5 column rebar lifting and Level 3 formwork stripping were affected, with about 3 hours lost for 18 steel fixers and 14 carpenters. Crews were moved to ground level rebar prefabrication and work resumed at 12. The consultant was informed by email and the client PM by phone.

2. Delay details

Activity affectedLevel 5 column rebar lifting and Level 3 formwork strip
CauseTower crane stopped as wind speed exceeded 45 km/h, as per the lifting plan
Started9am
Duration9am to 12 noon (about 3 hours)
Stated impactAbout 3 hours lost for 18 steel fixers and 14 carpenters
ResponsibleNot stated
MitigationCrews moved to ground level rebar prefabrication; work resumed at 12
NotifiedConsultant by email; client PM by phone
ReferenceNot stated

3. Work carried out

No.ActivityArea / locationRemarks
1Rebar prefabrication (crews redeployed during crane stoppage)Ground levelMitigation during crane stoppage

4. Issues and delays

No.IssueArea / locationSeverityAction
1Tower crane stopped due to wind speed over 45 km/h, per lifting plan; about 3 hours lostLevel 5 columns; Level 3 formworkHighCrews moved to ground level rebar prefabrication; work resumed at 12

5. Mitigation and next steps

Not reported in the notes.

6. Manpower

TradeNo.
Steel fixers18
Carpenters14
Total32

7. Plant and equipment

DescriptionCondition
Tower craneStopped 9am to 12 noon due to high wind; resumed at 12

8. Sign-off

Prepared by (Site Engineer)
NameAhmed Al-Harbi
Signature
Date
Reviewed by (Project Manager)
Name
Signature
Date
Received by (Consultant)
Name
Signature
Date

Appendix A: notes as received

Message 1, 05 Nov 2026, 13:57

Delay notice Al Noor Tower, Thursday 5 Nov. Tower crane stopped from 9am to 12 noon because wind speed went over 45 km/h, as per the lifting plan.

Message 2, 05 Nov 2026, 13:58

Activity affected: level 5 column rebar lifting and level 3 formwork strip. About 3 hours lost for 18 steel fixers and 14 carpenters.

Message 3, 05 Nov 2026, 13:59

Mitigation: crews moved to ground level rebar prefabrication. Work resumed at 12. Consultant informed by email, client PM informed by phone.

Written by Groundwork from the sender's own notes. Not valid until reviewed and signed.